The gas supply line project of 24 and 30 inches in the city of Zahedan was executed under the supervision of the Gas Company of Sistan and Baluchestan province and the consulting engineers of Naghsh Avaran Tos by Chavosh Rah Bana Company.

Main Operations of the Project:

  1. Execution of the 24-inch and 30-inch pipeline with thicknesses of 0.688 inches and 0.312 inches
  2. Construction of two T.B.S stations with a capacity of 10,000 cubic meters per hour
  3. Installation of a corrosion protection station (CPS)
  4. Implementation of an 8-inch distribution network with a pressure of 60 PSI
  5. Installation of pipe markers
  6. Construction of a valve chamber ranging from 6 inches to 30 inches along the pipeline route