Gas supply line of Zahedan city

Gas supply line of Zahedan 

The 24 and 30-inch feed gas project of the city of Zahedan was carried out under the supervision of Sistan and Baluchestan Gas Company and Consulting Engineers of Shahr-e Avarand Toos, by Chavosh rah bana co

:Main project operations

A:Run 24-inch and 30-inch lines with a thickness of 0.688 inches -0.312 inches

B:Implementation of two T.B.S stations with a capacity of 10,000 cubic meters per hour

C:Run CPS alarm protection station

D:Implementation of the 8-inch distribution network with a pressure of 60 PSI

E:Installing pipe markers

F:Run valve pits from 6 inches to 30 inches on the line